ARISEIA
  • Home
  • 2026 CONFERENCE
    • Full Agenda
  • Programs
  • About
    • Board of Directors
    • Executive Director & Staff
    • AriSEIA Members
    • Events
    • Jobs
    • Solar Customers
    • Myths Busted
    • Contact Us
  • Join
    • Code of Ethics
  • Donate
  • News

NEWS

See what AriSEIA is up to on the policy front.

Arizona Court of Appeals Rejects APS and Commission Challenges to Ruling Striking Down Solar Charges

10/29/2026

0 Comments

 
Read the Motion
The Arizona Court of Appeals has denied requests from Arizona Public Service (APS) and the Arizona Corporation Commission to reconsider its June 16, 2026 ruling striking down discriminatory charges imposed on APS customers with rooftop solar.

In its October 29 order, the Court reaffirmed that the Commission violated due process when it authorized solar-specific charges without adequate notice or an opportunity for affected parties to challenge them. The Court also clarified that its earlier ruling vacated the authorization for the Grid Access Charge (GAC) and legacy solar adjustment, leaving the Commission to determine its next steps.

Importantly, the Court rejected arguments from APS and the Commission that the burden of proof should fall on parties challenging the charges. Because the original decision was adopted in violation of due process, it was void and could not be presumed valid. APS, as the original applicant, retained the burden of justifying the charges.

The Court also rejected arguments that the subsequent rehearing corrected the constitutional violations, finding that parties were not afforded a full and fair opportunity to challenge the evidence supporting the charges.

On October 30, AriSEIA filed a motion requesting that the Administrative Law Judge in APS's pending rate case take judicial notice of the new order and consider it alongside the existing evidentiary record.

The ruling represents another significant victory for Arizona rooftop solar customers and reinforces that utilities cannot impose discriminatory charges without complying with fundamental due process requirements.
​

The Commission must now address the Court's ruling as it considers APS's pending rate application.
Case: Vote Solar et al. v. Arizona Corporation Commission, 1 CA-CC 25-0001 (consolidated). APS Rate Case: E-01345A-25-0105.
0 Comments

AriSEIA Files Exceptions in the TEP Rate Case

10/29/2026

0 Comments

 
Read the Filing
The Arizona Solar Energy Industries Association (AriSEIA) filed exceptions to the Recommended Opinion and Order in Tucson Electric Power's (TEP) rate case, urging the Arizona Corporation Commission to expand access to battery storage programs, improve rate design, and protect customers from unnecessary costs.

Expanding virtual power plants is a central priority. AriSEIA is asking the Commission to ensure that customers who lease their batteries can participate in TEP's virtual power plant (VPP) program and that third-party battery owners can receive compensation directly. AriSEIA is also pushing to expand VPP participation to commercial and industrial customers, who are currently excluded. These changes would allow more batteries to support the grid, reduce peak demand, and provide benefits to customers.

AriSEIA also opposes eliminating TEP's commercial battery storage tariff. Rather than abandon the program, TEP should improve it and remove barriers to participation.

The filing raises serious concerns about TEP's residential rate design. AriSEIA's analysis found that 52% of non-solar customers on TEP's residential demand time-of-use rate would save an average of $17.89 per month on a different rate. Meanwhile, a typical residential customer shifting 15% of peak electricity usage would save just $7.24 annually under TEP's proposed time-of-use rates. AriSEIA is seeking stronger customer protections and rates that meaningfully reward reducing peak electricity consumption.

AriSEIA also opposes Kroger's proposal to shift more commercial electricity costs into demand charges, supports a return on equity no higher than 8.2%, and objects to requiring customers to pay for utility industry association dues and Board of Directors fees.

Finally, AriSEIA is asking the Commission to require TEP to file its next general rate case by June 30, 2030, ensuring that customers do not wait years for another comprehensive review of utility rates and costs.
​
The Commission is expected to vote on TEP's rate case on November 17, 2026. AriSEIA urges the Commission to use this opportunity to expand clean energy participation, improve customer protections, and ensure that TEP's rates benefit customers and the grid.
0 Comments

AriSEIA Submits Additional Comments on Apache County Renewables Ordinance

10/12/2026

0 Comments

 
Apache County Board of Supervisors
P.O. Box 428
St. Johns, AZ 85936
 
Re: Proposed Article 8 Renewable Energy Ordinance (Draft 9.5) – Correcting the Record on Stakeholder Input
 
Dear Supervisors, Commissioners, and Staff,
 
The Arizona Solar Energy Industries Association (AriSEIA) writes ahead of the October 13 special work session to correct the record from the September 22 work session. At that session, a Commissioner asked why people from both sides were not helping with the ordinance. The response was that people supportive of renewable energy had been invited but were not present. The Chair added that developers had a lot of input in the early stages and should not be writing the ordinance. This leaves the impression that the County has heard only from opponents of renewable energy. That impression is false.
 
AriSEIA’s Comments Are On The Record And Remain Applicable
 
AriSEIA has taken part in this process since May 2025. Over the last year and a half, we submitted formal comment letters on December 3, 2025; January 12, 2026; March 4, 2026; May 23, 2026; and July 27, 2026. These letters included specific replacement language and an independent economic impact analysis by Elliott D. Pollack & Company. All of them are available at https://www.ariseia.org/news/category/apache-county.
 
AriSEIA is a trade association, not a project developer. Our comments are meant to produce an ordinance that is workable for any project, and they remain applicable to Draft 9.5. We did not submit new comments by the September 15 deadline because our earlier comments were not addressed. Draft 9.5 keeps or reinstates many provisions we have repeatedly flagged:

  • A one-megawatt applicability threshold that sweeps in small commercial and agricultural systems;
  • A requirement for interconnection and power purchase agreements before building permits;
  • A communications interference process that can trigger investigation and curtailment from a single complaint;
  • Definitions that pull gen-tie lines and transmission infrastructure into the ordinance; and
  • Requirements that outside agency and fire district approvals be in hand before a CUP can be heard.
 
The Ordinance Is Now Being Drafted From A Single Viewpoint
 
The Commission previously voted to advance a moratorium on renewable energy development, which the Board did not adopt. The Commission is now rewriting an ordinance that staff and stakeholders spent more than a year developing. At the August 25 and September 22 work sessions, the same small group of local residents who oppose these projects presented the revisions. They are also preparing rewritten sections and delivering them to Commissioners in advance of each meeting alongside staff. No comparable role has been offered to anyone with a different view. The results show this. On September 22 alone, the Commission added preferred criteria and intent language that:

  • Steer projects to the “most remote and sparsely populated areas” of the County;
  • Prefer sites at least 10 miles from visual resources;
  • Prefer sites downwind of populated areas;
  • Prohibit industrial wind construction in the Springerville Volcanic Field; and
  • State that the ordinance is meant to keep utility-scale renewable energy from becoming a routine use in Supervisor District III.
 
The Community Development Director asked during that session whether the point of these changes was to make the ordinance as restrictive as possible. That is a fair question, and the Board should be asking it too.
 
Many People Are Not Commenting Because They Have Been Ignored Or Do Not Feel Safe
 
Silence from supporters is not agreement. Many residents, landowners, and businesses have already commented and seen their input set aside. Others do not feel safe taking part. The Commission itself discussed this on August 25. One Commissioner’s colt and two calves were killed, and he received an online statement widely understood as a death threat. Another Commissioner resigned after he believed his water dispensing system, essential to his business, had been intentionally contaminated. The Commission decided at that meeting to redact property owner names from public application documents because of retaliation in the community. Multiple Commissioners have now stepped down. Conduct toward County officials became serious enough that the Stop Lava Run group publicly asked people to stop threatening them.
 
When the County’s own Commissioners and participating landowners need protection from retaliation, it is not reasonable to read the absence of public support as a lack of support.
 
Meetings Are Not Accessible To Much Of The County
 
Apache County is one of the largest counties in the country. Many residents live hours from St. Johns, and work sessions do not offer remote participation. Even apart from the safety concerns above, broad public input is not possible under these conditions. AriSEIA recommended remote participation in July and renews that request now.
 
A De Facto Moratorium Exposes The County To Legal Risk
 
Landowners in Apache County have property rights, including the right to lease their land for lawful uses. A county moratorium must meet the requirements of A.R.S. § 11-833, including specific written findings and a factual basis. A land use regulation that reduces the value of private property may also give rise to claims for just compensation under A.R.S. § 12-1134. Draft 9.5 itself states that the record must show the factual basis for each standard.
 
Staff has already warned about this. On September 22, the Community Development Director cautioned that making preferred areas mandatory would attract significantly more attention. An ordinance that uses setbacks, siting preferences, thresholds, and procedural barriers to achieve what a moratorium could not achieve directly invites the same challenges.
 
We are also concerned by the Chair’s statement on September 22. He said that although the new ordinance will not apply to pending applications, the County can add CUP conditions that match the draft. Applying unadopted standards to applications filed under the existing ordinance would add to that legal exposure.
 
AriSEIA’s Requests
 
AriSEIA respectfully asks the Board, the Commission, and staff to:

  1. Correct the record to reflect that AriSEIA and other stakeholders have submitted substantive comments throughout this process;
  2. Review and respond to AriSEIA’s prior comment letters before further action on Draft 9.5;
  3. Give stakeholders with differing views the same drafting role now given to opponents;
  4. Provide remote participation for all remaining work sessions and hearings;
  5. Evaluate pending CUP applications under the ordinance in effect when they were filed; and
  6. Return to the balanced framework developed with staff and stakeholders rather than adopting an ordinance that operates as a de facto prohibition.
 
AriSEIA remains a willing partner and would welcome the opportunity to meet with Supervisors, Commissioners, or staff.
 
Respectfully,
/s/ Autumn T. Johnson
Executive Director
AriSEIA 
(520) 240-4757
[email protected]
0 Comments

AriSEIA Submits Letter on Tucson BESS Ordinance

10/6/2026

0 Comments

 
City of Tucson Planning Commission
c/o Planning and Development Services
P.O. Box 27210
Tucson, AZ 85726-7210
Via email: [email protected]
 
RE: Agenda Item 5, CODE Tucson '26 Code Amendment (C8-25-03), Attachment E – Proposed Battery Energy Storage System Amendment
 
Dear Chair and Commissioners,
 
The Arizona Solar Energy Industries Association (AriSEIA) is the statewide trade association for the solar, storage, and electrification industry. We have engaged extensively on battery energy storage system (BESS) ordinances across Arizona, including in Maricopa County and the Cities of Mesa, Buckeye, Goodyear, and Surprise. We appreciate staff's work on the CODE Tucson '26 package and support the City's goal of creating a clear pathway for this critical infrastructure.
 
AriSEIA respectfully requests that the Commission continue the BESS amendment (Attachment E and the "Define battery storage use" item), or sever it from the CODE Tucson '26 package so the remaining amendments may proceed, to allow for a stakeholder process on the new proposal.
 
Request for Continuance
According to the staff memorandum, the BESS proposal reviewed at the August 26 and September 16 study sessions would have added BESS as part of the existing Distribution System use. After the September 16 study session, that approach was replaced with a standalone, two-tier use and eleven new use-specific standards.
 
This new version first appeared in the October 1 packet for the October 7 hearing. It has not been presented at a study session. It was not part of the surveys or community meetings described in the memorandum. To our knowledge, it has not been shared with the storage industry, Tucson Electric Power, or the commercial and institutional customers it would directly affect.
 
AriSEIA did not learn of the proposal until Friday, October 2. Three business days is not enough time for affected businesses, schools, hospitals, and developers to review it, let alone engage meaningfully. A short continuance would allow staff to hold at least one stakeholder meeting with industry, Tucson Electric Power, and the Tucson Fire Department, and return with a proposal tested against real projects. Severing the BESS item would let the rest of the package move forward on schedule.
 
AriSEIA's preliminary comments on the substance of the proposal follow.

1. Size Thresholds and Commercial and Industrial Systems
The proposed thresholds are far too small. A "Bulk Power" facility begins at 1 MW or 4 MWh, a system that may fit in one or two shipping-container-sized enclosures. Treating a system of that size like a large utility-scale facility will sweep in modest projects that pose no unique land use concerns.
 
The "Distributed" tier is even broader. It would regulate commercial, industrial, institutional, and microgrid systems starting at only 80 kWh, capturing:
·         batteries paired with rooftop solar at small businesses,
·         backup power at schools, churches, and hospitals,
·         battery-buffered EV charging,
·         storage at multifamily properties.
 
These customer-sited systems serve on-site load. They are already governed by the City's adopted building, electrical, and fire codes, and other Arizona jurisdictions have excluded them. Mesa expressly excludes accessory systems serving the enterprise functions of the on-site owner or tenant.[1] Maricopa County distinguishes utility-scale systems from customer-sited systems.[2]
The tier structure also leaves gaps. Behind-the-meter systems at or above 1 MW, and front-of-the-meter systems below 1 MW, fall into neither tier. Under the use tables, they would have no permitted path.
 
AriSEIA recommends eliminating the Distributed tier. All commercial, industrial, and institutional behind-the-meter systems should be exempt, and at a minimum any such system under 10 MW. The ordinance should apply only to front-of-the-meter, utility-scale facilities of 10 MW or greater.
At an absolute minimum, the City should follow the City of Surprise, which adopted a 5 MW threshold for accessory battery systems in its BESS ordinance on September 1, 2026.[3] Surprise has more direct experience with BESS safety than any jurisdiction in Arizona, and it concluded that systems of this size do not warrant the same treatment as utility-scale facilities. Tucson's proposed thresholds of 80 kWh and 1 MW are far below that benchmark.
 
2. Limiting the Ordinance to Lithium-Ion Technology
The proposed definition covers "chemical, electrochemical, or mechanical" storage. The standards that follow, however, are framed around lithium-ion thermal runaway and off-gassing. Technologies such as flow batteries, iron-air, sodium-based chemistries, and mechanical storage have different characteristics and risk profiles. There is no evidentiary basis for assuming that the separation distances, barrier walls, and hazard standards in this proposal are appropriate for them.
​
National Fire Protection Association (NFPA) 855 already contains technology-specific provisions for these systems. Applying lithium-ion-based zoning standards to every storage technology risks both over-regulating emerging technologies and locking in requirements the City may later need to undo. AriSEIA recommends the following definition:
 
"Battery Energy Storage System (BESS), Utility-Scale: A stationary lithium-ion battery energy storage facility with a rated power capacity of 10 MW or greater, located in front of the customer meter and designed for energy market participation or grid services. Systems installed behind the customer meter or primarily serving on-site load, including residential, commercial, industrial, and institutional systems, are exempt from this use and its associated standards. Energy storage technologies other than lithium-ion shall be classified as a Distribution System use and reviewed in accordance with the City's adopted building, electrical, and fire codes."
 
3. Zoning Districts and Solar-Plus-Storage
Bulk BESS is limited to industrial zones by right and to C-2, C-3, and P-I by special exception. Utility-scale storage is often best located in rural and large-lot areas near transmission and away from population centers. The special exception process already lets the City evaluate compatibility case by case.
 
AriSEIA recommends making utility-scale BESS eligible for special exception review in rural and large-lot districts. AriSEIA also supports the City’s previous consideration of classifying BESS as a utility distribution use. BESS should be allowed in the same zoning districts where Distribution Systems are currently permitted, including C-1, C-2, C-3, OCR-1, and OCR-2, subject to sensible and industry-vetted use-specific standards. This approach recognizes the role that energy storage plays in supporting electric system reliability while providing the City with clear review standards.
 
The ordinance should also state that BESS is a permitted accessory use to an approved solar facility, without a separate approval.
 
4. Separation Requirements
AriSEIA appreciates that the proposed 150-foot residential separation is consistent with Buckeye's adopted standard and the range identified by the American Planning Association.[4] Maricopa County requires 100 feet from lot lines.[5]
 
However, the separation should be measured to existing residential structures, not to a residential zoning district boundary line. A zoning boundary line may border vacant land, rights-of-way, or portions of a parcel hundreds of feet from any home. Measuring to the boundary line effectively expands the separation well beyond 150 feet. It does so without any corresponding safety benefit, because the stated purpose of the separation is to protect people. AriSEIA recommends:
 
"An outdoor utility-scale BESS shall be located no closer than one hundred fifty feet (150') from an existing residential dwelling unit, measured in a straight line from the outermost battery cabinet to the nearest exterior wall of the dwelling."
 
The additional 300-foot separation from schools, daycares, hospitals, senior living, and "high-occupancy assembly use" should be removed. These are the very facilities most likely to install batteries themselves for backup power and resilience, often inside or immediately adjacent to the occupied building. A rule that treats a battery 299 feet from a hospital as unacceptable, while the hospital may operate its own battery on site, is internally inconsistent and has no technical basis. "High-occupancy assembly use" is also undefined, which invites inconsistent application. The 150-foot standard measured to existing structures is sufficient.
 
The relief mechanism also needs revision. It allows only a 25% reduction, and only on a showing that a barrier wall achieves "identical safety metrics." Standard 7 already requires that wall, so the same mitigation is counted against the applicant twice. It should be replaced with the general waiver discussed below.
 
5. No Retroactive Application
Several provisions, including the abandonment standard, apply to "any BESS facility" without limitation. BESS facilities should be required to comply with the zoning requirements in effect when they are installed. They cannot practically be required to meet new standards retroactively. An existing facility cannot be relocated to satisfy a new separation distance. It cannot be rebuilt behind a wall designed after it was constructed. It cannot re-engineer equipment to meet a noise limit that did not exist when it was permitted. AriSEIA recommends adding:
 
"The requirements of this section apply only to BESS facilities for which a complete application is submitted after the effective date. Facilities installed, permitted, or with a complete application on file before the effective date shall be governed by the regulations in effect at that time. Routine maintenance, repair, and augmentation within the approved footprint shall not subject an existing facility to this section."
 
6. Hazard Evaluation and Reliance on National Standards
Standard 5 requires an applicant to demonstrate, to the satisfaction of the City, that "any potential failure scenario" can be contained on-site. That standard is subjective and open-ended, and no applicant can meet it with certainty. National standards already address this subject comprehensively. NFPA 855 requires:
·         a Hazard Mitigation Analysis,
·         an emergency response plan,
·         commissioning,
·         large-scale fire testing under UL 9540A for systems listed to UL 9540.[6]
 
AriSEIA recommends that Standards 3 through 5 expressly require compliance with the currently adopted edition of NFPA 855, UL 9540, and UL 9540A. Those submittals should be due at building permit, when equipment and design are known, rather than at zoning approval.
 
7. Noise
The proposed limits of 55 dBA at a commercial property line and 45 dBA at a residential property line are far too low. A 55 dBA limit at a commercial property line is roughly the level of normal conversation. It is quieter than the rooftop HVAC equipment found on virtually every commercial building in Tucson. The residential limit is quieter still.
 
These limits are not applied to other utility or mechanical uses. They would single out BESS in the same package in which the City is updating its general noise regulations. AriSEIA recommends that BESS be subject to the same noise rules as other land uses. In the alternative, the ordinance should use an objective limit of 65 dBA at the project boundary, demonstrated by a qualified acoustical engineer.
 
8. Indoor Requirement
Standard 11 requires BESS to be located entirely within an enclosed primary structure or parking garage, with any outdoor installation requiring a special exception. Requiring BESS to be placed within enclosed structures or parking garages runs counter to the direction of modern industry practice. Based on industry lessons learned from operating experience and battery incidents, the industry has moved towards outdoor BESS installations in non-occupiable enclosures, rather than locating batteries inside occupiable or enclosed buildings. Outdoor installations are the safer and more appropriate configuration for BESS.
.
Indoor installations generally trigger more demanding fire code requirements than outdoor ones. They are also harder for firefighters to access and ventilate. Outdoor siting in purpose-built enclosures is often the configuration fire officials prefer. Parking garages in particular are enclosed, occupied spaces that are poorly suited to battery placement.
 
The provision would also bar a standard outdoor cabinet behind a downtown building without a special exception, while pushing the same equipment into a less desirable indoor location. AriSEIA recommends removing Standard 11 and allowing outdoor installations in these zones subject to the same standards that apply elsewhere.
 
9. Walls and Landscaping
AriSEIA does not object to 8-to-10-foot screen walls where screening is appropriate. However, Standard 7 goes further. It requires every outdoor equipment yard to be enclosed by a reinforced masonry wall "designed to serve as a thermal and blast barrier." No national standard defines or calls for such a wall. NFPA 855 addresses explosion control at the enclosure level, and a solid perimeter wall can complicate ventilation and fire department access.
 
Standard 8 adds a mandatory 10-foot landscape border outside the wall, which increases land requirements and water use. AriSEIA recommends treating walls as screening rather than blast barriers. Staff should also have authority to approve alternative perimeter treatments where site conditions warrant, as Buckeye and Maricopa County allow.
 
10. Decommissioning and Abandonment
Standard 9 requires restoration to a "greenfield state." That is not a meaningful standard for sites that were parking lots or previously-developed  land before BESS construction. It also requires a recorded plan signed by the system operator before building permit, when the operator may not yet be known. Restoration should be to pre-construction condition, and the plan should be due before certificate of occupancy.
 
Standard 10 deems a facility abandoned after 12 months without operating or delivering power to the grid. The standard should:
·         apply only to utility-scale facilities installed after the effective date,
·         exclude periods of repair, augmentation, interconnection delay, and force majeure,
·         clarify what "deploy" means.
 
11. Waiver and Administrative Modifications
The ordinance should include a general waiver provision and administrative approval of routine modifications. AriSEIA recommends:
 
"The Zoning Examiner may grant a waiver from specific requirements of this section upon a finding that the proposed alternative provides equivalent or greater protection for public safety and compatibility with surrounding land uses."
 
"Administrative approval may be granted for modifications that do not increase the approved project footprint, reduce required separations, or materially alter approved access, emergency response, or fire protection features."
 
Conclusion
Battery storage is increasingly essential to grid reliability and affordability in Southern Arizona. A well-designed ordinance can protect residents while giving applicants a clear, workable path.
The current proposal does not do that. Its size thresholds are too small, and it reaches customer-sited systems that should be exempt. It applies lithium-ion-based standards to technologies they were not designed for, and measures separation to zoning lines rather than homes. It penalizes proximity to facilities that use batteries themselves, and it imposes noise and indoor-siting requirements that do not reflect real-world conditions or fire safety practices.
 
These issues can be resolved, but not in three business days. AriSEIA respectfully asks the Commission to continue or sever the BESS amendment, and we welcome the opportunity to work with staff on a revised proposal.
 
Respectfully,
/s/ Autumn T. Johnson
Executive Director
AriSEIA 
(520) 240-4757
[email protected]
 
[1] Mesa City Code § 11-31-37; Mesa Resolution 12441 (Dec. 1, 2025), https://www.mesaaz.gov/files/assets/public/v/1/business-development/devsvcs/codesords/bess-adoption-by-ref-doc.pdf.
[2] Maricopa County Zoning Ordinance art. 603.10, https://esd.maricopa.gov/DocumentCenter/View/4785/P-18---Zoning-Ordinance-PDF?bidId=.
[3] City of Surprise, Ordinance No. [____] (Sept. 1, 2026), Case FS23-1041, Battery Energy Storage System Overlay.
[4] American Planning Association, Zoning Practice: Battery Energy Storage Systems 10 (Mar. 2024), https://planning-org-uploaded-media.s3.amazonaws.com/publication/download_pdf/Zoning-Practice-2024-03.pdf; City of Buckeye Development Code § 3.2, https://library.municode.com/az/buckeye/codes/code_of_ordinances?nodeId=CD_ORD_CH7DECO.
[5] Maricopa County Zoning Ordinance art. 603.10, supra note 2.
[6] NFPA 855, Standard for the Installation of Stationary Energy Storage Systems (2023 ed.); UL 9540, Energy Storage Systems and Equipment; UL 9540A, Test Method for Evaluating Thermal Runaway Fire Propagation in Battery Energy Storage Systems.
0 Comments

AriSEIA Submits Letter to ACC on Apache County Renewables Ordinance

10/4/2026

0 Comments

 
FIND THE FILING HERE
Arizona Corporation Commission
1200 West Washington Street
Phoenix, Arizona 85007
 
Re: CG Apache County Solar LLC and CG Apache County Wind LLC, Docket Nos. L-21365A-25-0198-00250 and L-21364A-25-0198-00250
 
Dear Chairman and Commissioners,
 
The Arizona Solar Energy Industries Association (AriSEIA) is a nonprofit trade association. It represents Arizona's solar, storage, and electrification industry. AriSEIA regularly takes part in proceedings before the Arizona Corporation Commission and has been directly and continuously involved in Apache County's renewable energy ordinance process.
 
AriSEIA submits this letter in response to public comments asking the Commission to hold off on voting on the Certificate of Environmental Compatibility (CEC) for the Lava Run Interconnection Project until Apache County revises its existing renewable energy ordinance. AriSEIA respectfully urges the Commission to reject that request and proceed to a vote. There are three reasons. The request has nothing to do with the project before the Commission. The Line Siting Committee has already considered it. And it would tie this proceeding to a county process with no end date in sight.
 
1. Apache County already has a renewable energy ordinance.
These comments assume that Apache County lacks the rules it needs to govern renewable development. That is not the case. The County has a renewable energy ordinance in effect today, and applicants can submit projects under it. The ongoing revision updates that ordinance; it does not fill a regulatory gap. The pending revision does not stop the County from exercising its land use authority over generation facilities now. It also has no bearing on the Commission's ability to act on this CEC.
 
2. The ordinance does not apply to transmission lines, and the revised ordinance will not either.
The Lava Run Interconnection Project is a 345-kV generation tie transmission line with associated interconnection facilities. The Commission's jurisdiction over that line comes from A.R.S. §§ 40-360 et seq. Apache County's renewable energy ordinance, both the current version and the one being revised, governs renewable generation facilities. It does not regulate transmission lines. Throughout the revision process, AriSEIA has consistently urged the County to keep transmission and interconnection facilities outside the ordinance. Those facilities are already covered by separate state and federal frameworks, including this one. Delaying a decision on a transmission line until the County finishes an ordinance that will not govern that line serves no purpose.
 
3. The County's revision process has no end date.
AriSEIA has taken part in the revision of Apache County's ordinance since May 2025. Since then, AriSEIA has submitted multiple formal comment letters, and the draft has gone through eight versions. In July 2026, instead of adopting the ordinance, the Board of Supervisors considered sending it to another subcommittee for more review. It is unclear when, or whether, the County will finish this ordinance. Making the Commission's vote depend on that outcome would suspend this proceeding indefinitely.
 
4. The ordinance process has been marked by a moratorium attempt, resignations, and harassment.
The body working on the ordinance has already tried to advance a moratorium on renewable energy development. The Board of Supervisors never took up that proposal. Three Planning and Zoning commissioners have since stepped down. People taking part in the process have been harassed and threatened. AriSEIA raised these concerns directly with the County in July 2026, noting that no stakeholder should fear retaliation for participating in a local government process. Arguing that a state certificate should wait on a process in this condition is not a good faith argument. A delay would reward the conduct that has stalled the County's work.
 
5. The Line Siting Committee has already considered this issue.
The Arizona Power Plant and Transmission Line Siting Committee held two full hearings on this matter. The status of Apache County's ordinance was before the Committee, and the Committee made its decision with that information in hand. The people raising this argument now are asking the Commission to reopen a question the Committee has already heard and resolved. That, too, is not a good faith argument.
 
Conclusion
The Lava Run Interconnection Project is a transmission line properly before the Commission under A.R.S. §§ 40-360 et seq. Apache County's renewable energy ordinance, existing or revised, does not govern it. The Line Siting Committee has already weighed the arguments for delay after two full hearings. AriSEIA respectfully urges the Commission to decline the request to postpone and to proceed to a vote on the Committee's Decision on Remand.
 
For the Commission's reference, AriSEIA's prior comment letters to Apache County on the renewable energy ordinance are available at: https://www.ariseia.org/news/category/apache-county.
 
Respectfully,
/s/ Autumn T. Johnson
Executive Director
AriSEIA 
(520) 240-4757
[email protected]
​
0 Comments
    Picture

    AriSEIA News

    Keep up with the latest solar energy news!

    Archives

    October 2026
    September 2026
    August 2026
    July 2026
    June 2026
    May 2026
    April 2026
    March 2026
    February 2026
    January 2026
    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    November 2021
    July 2021
    November 2020
    October 2020
    September 2020
    August 2020
    June 2020
    April 2020
    January 2020
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018

    Categories

    All
    ACC Updates
    ADOT
    Apache County
    APS
    AriSEIA Update
    Arizona Department Of Environmental Quality (ADEQ)
    ASU
    Autonomous Vehicles
    Auxin
    Avoided Cost
    AZGFD
    AZ Legislature
    BBB
    BESS
    BLM
    Chino Valley
    City Of Buckeye
    City Of Eloy
    City Of Flagstaff Updates
    City Of Goodyear
    City Of Mesa
    City Of Tempe Updates
    City Of Tucson
    City Of Wilcox
    Cochise County
    Community Benefit Agreements
    Community Solar
    Consumer Protection
    Coolidge Expansion
    DDSR Aggregation
    DG
    Election
    Electric Vehicles
    Electrification
    Energy Rules
    EVs
    Federal Policy
    FTC
    GAC
    Gila Bend
    Governor's Office
    Grid Access Charge
    HB2101
    Hopi
    Hydrogen
    Interconnection
    IRA
    IRP
    Just Transition
    Line Siting
    Local Government
    Maricopa County
    Meters
    Mohave County
    Municipalities
    Navajo County
    Navajo Generating Station Updates
    Navajo Nation Energy Updates
    Newsletter
    Press Release
    Project Bella
    Proposition 127
    Public Lands
    Rate Cases
    RCP
    Resource Planning
    REST
    ROC
    SolarApp
    Solar For All
    SRP Updates
    SSVEC
    State Energy Office
    Storage
    Sulphur Springs
    SunZia
    Surprise
    Tariffs
    TEP
    Transmission
    Trico
    Tucson Updates
    UNSE
    Utilities
    Utility Scale
    Value Of Solar
    VPP
    Yavapai County
    Zoning

    RSS Feed

Picture
The Arizona Solar Energy Industries Association (AriSEIA) is a 501(c)(6) non-profit trade association representing the solar, storage, and electrification industry, solar-friendly businesses, and others interested in advancing complementary technologies in Arizona. The group's focus is on education, professionalism, and promotion of public policies that support deployment of solar, storage, and electrification technologies and renewable energy job growth and creation.

FOLLOW Us

Donate
BECOME A MEMBER
Join Our Email List
Copyright © 2019 AriSEIA - All Rights Reserved 





  • Home
  • 2026 CONFERENCE
    • Full Agenda
  • Programs
  • About
    • Board of Directors
    • Executive Director & Staff
    • AriSEIA Members
    • Events
    • Jobs
    • Solar Customers
    • Myths Busted
    • Contact Us
  • Join
    • Code of Ethics
  • Donate
  • News