ARISEIA
  • Home
  • 2025 CONFERENCE
    • Full Agenda
  • Programs
  • About
    • Board of Directors
    • Executive Director & Staff
    • AriSEIA Members
    • Events
    • Jobs
    • Solar Customers
    • Myths Busted
    • Contact Us
  • Join
    • Code of Ethics
  • Donate
  • News

NEWS

See what AriSEIA is up to on the policy front.

AriSEIA Sends Letter to SRP on Resource Plan

9/27/2023

0 Comments

 
Salt River Project
1500 N. Mill Avenue
Tempe, AZ 85288
 
RE: Integrated System Plan and Stakeholder Engagement
 
Salt River Project and Board,

The Arizona Solar Energy Industries Association (AriSEIA) requested to be a part of the Integrated System Plan (ISP) stakeholder group in 2022. That request was denied. AriSEIA also requested to be included in the Sustainability Advisory Council and, to date, that has also not been granted. It is unclear why AriSEIA continues to be excluded from all formal SRP stakeholder processes. Therefore, AriSEIA submits the following comments on Item 4 of the October 2nd Board Meeting:

SRP should be required to issue All Source Requests for Proposals (ASRFPs) for all major procurements of generating resources. Those ASRFPs should be vetted through the ISP stakeholder process, as Arizona Public Service (APS) has started to do. The ISP stakeholder process should not exclude stakeholders that request inclusion, especially if they are well established organizations that participate in the resource planning processes of every other major utility in the state. Additionally, no stakeholder process should purposely exclude an entire stakeholder segment, such as renewable energy organizations. Such a stance needlessly excludes valuable expertise from what should be a technically robust process. Meetings should also be virtual or hybrid. In person meetings, such as has been the case for the last two, exclude many stakeholders. Stakeholders that are out of the Phoenix metro area, have small children, or cannot devote multiple hours to commuting to and from SRP are excluded. The other major utilities all have remote options for stakeholder participation.

Further, the ISP stakeholder process should be meaningful. There should be an exchange of information in both directions and the utility should be willing to make modifications based on stakeholder feedback, run requested portfolios, and provide the modeling inputs and results to stakeholders. Board members should familiarize themselves with the Arizona Corporation Commission (ACC) Integrated Resource Plan (IRP) process and should hold SRP to a similar standard, as you all serve as the regulator of SRP.

SRP has been holding meetings on the ISP for more than two years. The board should be voting on a resource plan, not three vague slides called “strategies.” That is not adequate oversight of an unregulated monopoly. The “strategies” provide no meaningful information as to what the utility plans to do regarding RFPs, procurement, or implementation of their sustainability goals. The 2017-2019 resource plan was much more detailed and it completely neglected major procurements, such as the Coolidge expansion.
​
SRP is the only major utility in the state that does not have an exit date for all coal; does not have a mass based carbon emissions goal; and has pursued major gas plant expansions that were never in a resource plan or RFP. The board should demand that the company do better. You are the only oversight on the second largest utility in the state.
Sincerely,
 
/s/ Autumn T. Johnson
Executive Director
AriSEIA 
(520) 240-4757
[email protected]
0 Comments

AriSEIA Submits Letter to Line Siting Opposing Requirement of System Impact Studies to Obtain a Certificate of Environmental Compatibility

9/22/2023

0 Comments

 
Line Siting Committee
Arizona Corporation Commission
1200 W. Washington Street
Phoenix, AZ 85007-2996
 
RE:      Obed Meadows CEC, Docket No. L-21254A-23-0184-00222
 
Chairman and Committee Members,
 
The Arizona Solar Energy Industries Association (AriSEIA) submits this letter in opposition to requiring a System Impact Study (SIS) in advance of obtaining a Certificate of Environmental Compatibility (CEC). The legal briefs of the applicant, Arizona Public Service (APS), and Tucson Electric Power (TEP) all agree that such a requirement is outside the authority of the Line Siting Committee. Further, such a requirement would needlessly delay gen-tie applications. The legislature via HB 2496 and the Commission via dockets RLS-00000A-23-0251 and ALS-00000A-22-0320 and the Governor’s Office via signature of HB 2496, have all indicated that the goal of the State of Arizona is to expedite these renewable energy projects, not add additional bureaucratic hurdles and delay. The Line Siting Committee has been issuing CECs without SISs and it is not clear why that would need to change now.
 
Testimony in this case, as well as the legal brief of APS, make clear that the absence of a SIS is not the fault of the applicant. There is a backlog of these studies, which is outside the control of renewable energy developers. Transmission Providers throughout the state of Arizona, including the state’s two largest utilities: APS and Salt River Project (SRP), are currently working through significant queue reforms to address interconnection backlogs. Proposed queue reforms will materially impact the timeline of interconnection studies, the requirements for projects to enter and stay in the interconnection queue, and the commercial expectations of projects when bidding into Request for Proposals (RFPs). Such queue reform is expected to introduce withdrawal penalties that will fundamentally change the way a project is developed, creating a new model whereby a project is incentivized to first acquire all its permits (including a CEC), obtain off-take, and then enter the interconnection queue. Having a SIS prior to filing for a CEC would be counter to the intent of queue reform, and a third-party power flow study would be expensive and redundant to already required utility interconnection studies. While the timeline around queue reform implementation is uncertain, FERC Order 2023 indicates an effective date is likely by the end of 2023 or in early 2024.
 
AriSEIA strongly advocates that the Line Siting Committee adhere to the purpose and intent of the Line Siting statute (A.R.S. 40-360.06); its prior decisions on applications that did not have a SIS; the clear intent of the legislature, Governor’s Office, and Commission to reduce Line Siting delay; and the Federal Energy Regulatory Commission’s (FERC) queue reform process and not require a SIS prior to obtaining a CEC. A requirement to have a SIS may have unintended consequences that limit the ability for projects to reach operations in a timely manner.
 
Sincerely,
 
/s/ Autumn T. Johnson
Executive Director
AriSEIA 
(520) 240-4757
[email protected]
​
0 Comments

    AriSEIA News

    Keep up with the latest solar energy news!


    Archives

    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    November 2021
    July 2021
    November 2020
    October 2020
    September 2020
    August 2020
    June 2020
    April 2020
    January 2020
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018

    Categories

    All
    ACC Updates
    ADOT
    Apache County
    APS
    Arizona Department Of Environmental Quality (ADEQ)
    ASU
    Autonomous Vehicles
    Auxin
    Avoided Cost
    AZ Legislature
    BBB
    BESS
    BLM
    Chino Valley
    City Of Buckeye
    City Of Eloy
    City Of Flagstaff Updates
    City Of Mesa
    City Of Tempe Updates
    Community Solar
    Consumer Protection
    Coolidge Expansion
    DDSR Aggregation
    DG
    Election
    Electric Vehicles
    Electrification
    Energy Rules
    EVs
    Federal Policy
    FTC
    GAC
    Governor's Office
    Grid Access Charge
    HB2101
    Hopi
    Hydrogen
    Interconnection
    IRA
    IRP
    Just Transition
    Line Siting
    Local Government
    Maricopa County
    Meters
    Mohave County
    Municipalities
    Navajo County
    Navajo Generating Station Updates
    Navajo Nation Energy Updates
    Newsletter
    Project Bella
    Proposition 127
    Public Lands
    Rate Cases
    RCP
    Resource Planning
    REST
    ROC
    SolarApp
    Solar For All
    SRP Updates
    SSVEC
    State Energy Office
    Storage
    Sulphur Springs
    SunZia
    Surprise
    Tariffs
    TEP
    Transmission
    Trico
    Tucson Updates
    UNSE
    Utilities
    Utility Scale
    Value Of Solar
    VPP
    Yavapai County
    Zoning

    RSS Feed

Picture
The Arizona Solar Energy Industries Association (AriSEIA) is a 501(c)(6) non-profit trade association representing the solar, storage, and electrification industry, solar-friendly businesses, and others interested in advancing complementary technologies in Arizona. The group's focus is on education, professionalism, and promotion of public policies that support deployment of solar, storage, and electrification technologies and renewable energy job growth and creation.

FOLLOW Us

JOIN ARISEIA
Donate
Join Our Email List
Copyright © 2019 AriSEIA - All Rights Reserved 





  • Home
  • 2025 CONFERENCE
    • Full Agenda
  • Programs
  • About
    • Board of Directors
    • Executive Director & Staff
    • AriSEIA Members
    • Events
    • Jobs
    • Solar Customers
    • Myths Busted
    • Contact Us
  • Join
    • Code of Ethics
  • Donate
  • News